Holiday Manor Co-Op, Inc.

PARK PROGRESS REPORT

NAPLES, FL 34114

*UP COMING MEETING*


We will be having an Emergency Preparedness Meeting on May 29th at 10am in the Recreation Hall for residents who are full time in the park. We will be giving out local information on emergency numbers, shelters and general info. If you are in the park for Hurricane Season, you are urged to attend.



Pool Status : 

  • The pool will be closed through May 31st. The repairs are taking longer than anticipated due to additional concerns that have risen that need to be addressed. 
  • Occupancy sensors have been installed inside the pool bathrooms. 


Club House Progress:

  • The clubhouse awning is currently being addressed as it did not pass inspection by the county.  
  • The shuffle board awning has been inspected and passed.
  • The shuffle board lights have been repaired.
  • The women's inside bathroom has had all mold removed and the bathroom has been repaired. 
  • The remaining portion of clubhouse floor will be striped and waxed on Tuesday. This is the small area where the cabinet was removed due to mold. 
  • The laundry room ceiling tiles have been installed.
  • The laundry room door has been installed.


Additional Progress Updates Throughout The Park:

  • This screen room project is progressing. Once we have a start date, we will be sure to let you know. 
  • The front wall, entrance sign, community back flow and pump houses have been painted.
  • The new website should be up and running by end of the month.
  • The sewer lining project is expected to begin June 3rd. 










Club House Photos:

The Rec Hall, Holiday Manor Office and Laundry Room floors have all been cleaned, stripped and waxed. You can see the difference between the first photo (before) and the other 3 (after). They did a great job and the floors look absolutely great! The Rec Hall and Laundry Room will be reopened on Monday, May 6, 2019.









Shuffle Board Courts Photos:

The awnings have been installed on the Shuffle Board Courts and look great! The Shuffle Board Courts will be reopened on Monday, May 6, 2019.